Cape Town removes ECSA professional sign-off for qualifying SSEG under 100 kVA

The City of Cape Town says an ECSA-registered professional no longer has to sign off SSEG systems below 100 kVA in categories A1 and A2. This removes one step for many residential and smaller commercial installations—but it does not remove City authorisation or electrical compliance duties.

THE KEY CHANGE

One sign-off requirement has changed. The compliance process remains.

The City describes the change as effective immediately. A precise publication date was not shown in the reviewed notice, so applicants should confirm how the change applies to an application already in progress.

What remains compulsory

  • Apply to the City and obtain the required SSEG authorisation.
  • Select an inverter on the City’s current approved-equipment list.
  • Install and test the electrical work correctly and issue the applicable Certificate of Compliance.
  • Submit the drawings, equipment information and commissioning records required for the project.
  • Meet the relevant meter, tariff and export-control requirements.
Five-step SSEG compliance path from design to commissioning
A practical project path. The documents needed can differ by system category and application.

Important transition warning

Some older wording on the City’s own information page still refers to an ECSA professional signing the commissioning report. Until every City document is aligned, do not guess: confirm the document set for pending or new applications with ElectricityApplication.Queries@capetown.gov.za.

Metering and export rules have not disappeared

Solar system exporting through an AMI meter

Feed-in system

An approved AMI meter and the applicable tariff arrangements remain relevant where energy is exported to the City network.

Solar system with reverse power flow blocked

Non-export system

Where export is not permitted, the required reverse-power-flow blocking or approved export limitation must be correctly designed, set and verified.

Approved inverter list

The City’s linked approved photovoltaic inverter list is dated 11 September 2026. Check the exact manufacturer, model and variant before equipment is ordered—similar product names are not enough.

Practical actions before the next installation

  1. Classify the system first. Confirm the SSEG category, capacity, export arrangement and supply type.
  2. Check the exact inverter. Verify the model against the latest City list before quoting or purchasing.
  3. Confirm the application pack. Ask the City what it expects where older and newer instructions differ.
  4. Keep the technical file complete. Retain the CoC, test results, settings, schematics, data sheets and commissioning records.
  5. Train against current requirements. Visit RSA Electrical Training for Installation Rules Paper 1 and Paper 2 preparation.

Official sources

City of Cape Town: Apply for authorisation to install an embedded generation system ↗

City of Cape Town: Approved photovoltaic inverter list (PDF) ↗

This article is a practical summary, not a substitute for the applicable standard, legislation or a project-specific City decision. Requirements and linked documents can change.

PLANNING A SYSTEM?

Talk through the installation before buying equipment.

WhatsApp Rob ↗

Check distribution-board labels before issuing a CoC

The 9 October briefing identified no new binding requirements in the areas it reviewed. ECA(SA)’s 7 October technical note focused on checking that labels match the installation and remain readable over time.

For current Cape Town solar approval and metering information, see the 25 November SSEG update and its City of Cape Town links.

Industry guidance from ECA(SA)

  • Trace circuits where their purpose is unclear. Check that the breaker description matches the circuit it actually controls.
  • Replace missing, incorrect or illegible labels. Use durable markings and check them again after alterations.
  • Check alternative supplies. Confirm that the required notices identify sources such as an inverter or generator at the main switch and affected boards, where applicable.

Certificate of Compliance requirement

The electrical test report’s labelling inspection item must be satisfied. Under regulation 9(3) of the Electrical Installation Regulations, the registered person must withhold the CoC until any fault or defect found before issue has been rectified.

Power quality discussion

ECA(SA) announced an online Power Quality Industry Think Tank for 30 November 2026. The session covers practical issues including harmonics, voltage fluctuations and phase imbalance.

Sources

Department of Employment and Labour · Electrical Installation Regulations, 2009 (PDF)

ECA(SA) · Correct and permanent marking and labelling

ECA(SA) · Power Quality Industry Think Tank

Prepare for Installation Rules Paper 1 and Paper 2

Explore Installation Rules training
Call Rob 071 533 6466